• Feasibility study to evaulate expanding existing building or buy and renovate another building.
  • Final design to renovate a newly acquired 7,200 s.f building.
  • Renovation included township offices, waiting room, public meeting room and police station.
  • Project completed April 1996 - Construction cost $225,000.

  • Interior and exterior renovation to provide new entrances to the building's pool, including an accessible exterior ramp and a new interior stair tower.
  • Completed April 1998 - Construction cost $110,000.


  • Interior renovations to the pool and locker room facility.
  • Work to include complete renovation of locker rooms  to provide for accessibility  and general improvements; new HVAC and dehumidification system; pool deck resurfacing; new seating; roof structural changes; and new finishes throughout. 
  • Project is awaiting funding. Estimated construction cost $650,000.



  • Interior renovations required to install a fully accessible, (3) stop, hydraulic elevator.
  • Work to include installation of masonry hoistway, relocation of some MEP systems, designed tie-in to existing finishes at each floor level. 
  • Project is awaiting funding. Estimated construction cost $190,000.

 


Manheim Township  
  • Renovation and addition to township administration offices. 
  • Design to meet current and future needs for office space, meeting rooms and storage space.
  • Project also includes improved configuration of office workstations. 
  • Construction completed May 2001, Construction Cost $1,000,000.  

 